Office build-out and lease workbook
Medical build-outs typically run $150–$400 per usable square foot depending on plumbing, mechanical, and imaging needs. Always demand a healthcare-experienced GC. Negotiate at least $40/sf TI allowance on a 5-year lease and confirm permit timelines before signing — most delays are permitting, not construction.
By Jordan Alderman, MBA, CMPE · Reviewed by Rania Hassan, JD, CHC · Last reviewed · Methodology
Disclosure: Independent editorial. No pay-for-placement, no affiliate rankings. Full editorial standards.
Who this is for: Physicians and administrators opening a new location or relocating.
Site selection
- Drive-time analysis vs target patient population
- Payer-mix density (commercial vs Medicare vs Medicaid)
- Referring physician proximity
- Parking ratio (min 4 per 1,000 sf for primary care)
- Visibility + signage rights
- ADA accessibility on entrance, restrooms, exam rooms
Lease negotiation
- 5-year with 5-year option is standard; longer for expensive build-out
- TI allowance $40–$100/sf depending on shell condition
- Base rent + NNN (Net-Net-Net) — confirm cap on NNN increases
- Free rent during build-out (typically 3–6 months)
- Exclusive use clause (no competing specialty in center)
- Assignment / subletting rights
- Right of first refusal on adjacent space
- Landlord permit-delay remedy
Space program (typical primary care, 4-provider)
- 8–12 exam rooms (2–3 per provider)
- 2 procedure rooms
- 1 lab draw room
- Nurse station / MA workstation
- Physician offices (1 per provider or shared)
- Reception + waiting (1.5–2 sf per patient/hour)
- Business office / billing
- Break room + staff restroom
- Storage + IT closet
- Total: 3,500–5,500 usable sf
Build-out timeline (16–28 weeks typical)
- Space plan + architect (weeks 1–4)
- Permits (weeks 3–10 — varies wildly by jurisdiction)
- GC bidding + selection (weeks 4–7)
- Construction (weeks 8–20)
- Furniture, fixtures, equipment install (weeks 18–24)
- IT / low-voltage cabling (weeks 16–22)
- Final inspection + CO (weeks 24–26)
- Move-in + operational shakedown (weeks 26–28)
Equipment planning
- Exam room package (table, stool, otoscope, BP, etc.)
- Procedure equipment specific to specialty
- Refrigerated vaccine storage with alarm + logging
- Autoclave for sterilization if in-office procedures
- Point-of-care lab if applicable (CLIA-waived only if not CLIA-certified)
- Imaging: X-ray requires state licensing + shielding — plan permitting for 4–8 weeks